Project Narrative
Project Overview
Columns were received at the workshop, fabrication was completed, and the structure was installed on site in Perdeberg. The installation was reviewed and approved by the client.
Scope of Work
- Workshop fabrication and on-site installation of the primary steel structure
- Roof and wall sheeting completed in a four-day follow-on phase
- Final touch-ups and close-out completed
Execution Method
After receiving the columns at the workshop, the team completed fabrication in sequence, transported members to site, and installed the frame with a six-person crew. Sheeting was then completed in four days.
Why This Approach
The client requested a 15x30 portal-frame design with two 7.30m link-to bays to meet required structural performance and layout use.
Major constraint: The sheeting phase had to be executed quickly to complete close-out within programme.
Results
The full structure was delivered safely and successfully, with sheeting and final works completed and accepted by the client.
Completion Highlight
Completed in approximately two to three weeks, with final completion and approval recorded by April 3, 2026.
